Question: While applying the logical relationships to the project activities, a project manager must be careful not to: Have closed loops relationships between activities Have FF
While applying the logical relationships to the project activities, a project manager must be careful not to:
Have closed loops relationships between activities Have FF relationships for the critical activities Have FS relationships for the non-critical activities Select the relationship with the highest impact