Question: You are a non-technical project manager. Two highly skilled and knowledgeable resources on your project are in conflict over the best technical solution to meet
You are a non-technical project manager. Two highly skilled and knowledgeable resources on your project are in conflict over the best technical solution to meet a project requirement. However, this is not affecting the project schedule. Who is initially responsible for the conflict resolution?
The project sponsor is initially responsible for the conflict resolution.
The project manager is initially responsible for the conflict resolution.
Both team members are initially responsible for the conflict resolution.
Either of the team members is responsible for the conflict resolution.