Question: Adam is a non-technical project manager. His project's two highly skilled resources - Sid and Sandeep, conflict with the best technical solution to meet a
Adam is a non-technical project manager. His project's two highly skilled resources - Sid and Sandeep, conflict with the best technical solution to meet a project requirement. However, it is not impacting the project schedule.
Who is initially responsible for the resolution of the conflict?
A. The project sponsor B. The project manager C. Both team members D. Either of the team members