Question: . You are managing a project that is on schedule with 60 work packages completed. One day a stakeholder tells you that she has found
. You are managing a project that is on schedule with 60 work packages completed. One day a stakeholder tells you that she has found a critical product function that was omitted in the project plan. To solve this problem you should:
a) Tell the stakeholder to keep quiet and maybe nobody will notice
b) Communicate the error to senior management
c) Update the project schedule and budget to reflect the necessary changes
d) Submit a change request to the change control board and rebaseline the project