Question: You are the project manager for a project and have just entered the third year of a scheduled four-year project. You need to evaluate new
You are the project manager for a project and have just entered the third year of a scheduled four-year project. You need to evaluate new risks that have arisen since the project began. What agenda item do you need to add to your next team meeting?
Variance and trend analysis Process Improvement Plan Risk audit Risk re-assessment