Question: You are the project manager for a project and have just entered the third year of a scheduled four year project. You need to evaluate


You are the project manager for a project and have just entered the third year of a scheduled four year project. You need to evaluate new risks that have emerged since the project began. What should you perform to provide this information?

A. Variance and trend analysis B. Process Improvement Plan C. Risk audit D. Risk re-assessment

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!