Question: You have overheard two functional managers arguing about the impacts that your project will have on their departments. What is your best response? Do nothing
You have overheard two functional managers arguing about the impacts that your project will have on their departments. What is your best response?
Do nothing Analyze and report to each manager the impact your project will have on their departments in terms of time and resources required and the relative enterprise priority of your project Inform the managers that the project sponsors already considered this impact when they decided to implement the project Put in advance requests for resources from each department