Question: Your construction project is in execution, and you require a major change to one of your supplier agreements. Can you directly make this change with

Your construction project is in execution, and you require a major change to one of your supplier agreements. Can you directly make this change with mutual consent of the supplier during the Control Procurements process, or do you have to visit the Perform Integrated Change Control process, as well?

The change request needs to be approved through the Control Procurements process prior to making the change through the Integrated Change Control process.

The change request can be directly processed through the Control Procurements process since the change requests only affects a particular supplier agreement.

The Control Procurements process is about identifying variances.

The supplier contract can directly be altered through the Perform Integrated Change Control process.

The change request needs to be approved through the Perform Integrated Change Control process prior to making the change through the Control Procurements process.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Fraud Examination Questions!