Question: Compute (a) Cycle time, (b) Value-added time, (c) Non-value-added time, (d) Cycle efficiency using the following information for a manufacturer. 2.10 days Move time. 0.75

Compute

(a) Cycle time,

(b) Value-added time,

(c) Non-value-added time,

(d) Cycle efficiency using the following information for a manufacturer.

2.10 days Move time. 0.75 days Process time. 0.50 days Wait time. 0.15 days Inspection time..

2.10 days Move time. 0.75 days Process time. 0.50 days Wait time. 0.15 days Inspection time..

Step by Step Solution

3.53 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Process time 210 days Inspection time 050 days Move ... View full answer