Question: Compute (a) cycle time, (b) value-added time, (c) non-value-added time, and (d) cycle efficiency using the following information for a manufacturer. (Round your answers to

Compute (a) cycle time, (b) value-added time, (c) non-value-added time, and (d) cycle efficiency using the following information for a manufacturer. (Round your answers to 2 decimal places.)

Process time 2.10 days

Inspection time 0.50 days

Move time 0.75 days

Wait time 0.15 days

I need help with answer D (cycle efficiency using the following information for a manufacturer.)