Question: 11. Two projects, A and B, are analyzed using ranking present worth analysis with MARR at i%. It is found that PW(A) . PW(B). If

11. Two projects, A and B, are analyzed using ranking present worth analysis with MARR at i%. It is found that PW(A) . PW(B). If MARR is changed to

(i 1 1)%, what will be the relationship between PW(A) and PW(B)?

a. PW(A) . PW(B)

c. PW(A) , PW(B)

b. PW(A) 5 PW(B)

d. Cannot be determined without the cash fl ow profi les