This problem continues the Piedmont Computer Company situation from Chapter 18. Piedmont Computer Company uses a job

Question:

This problem continues the Piedmont Computer Company situation from Chapter 18. Piedmont Computer Company uses a job order costing system in which each batch manufactured is a different job. Piedmont Computer Company assigns direct materials and direct labor to each job. The company assigns labor costs at $25 per hour. It allocates manufacturing overhead to jobs based on a predetermined overhead allocation rate, computed as a percentage of direct labor costs.

At the beginning of 2020, the controller prepared the following budget:

Manufacturing overhead

$  290,000

Direct labor costs

$ 1,160,000

In November 2020, Piedmont Computer Company worked on several jobs. Records for two jobs appear here:


Job 721

Job 722

Direct labor hours

780 hours

60 hours

Direct materials

$ 23,400

$ 2,500


Requirements

1.  Compute Piedmont Computer Company’s predetermined overhead allocation rate for 2020.

2.  Compute the total cost of each job.

3.  Why does Piedmont assign costs to jobs?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Horngrens Accounting The Managerial Chapters

ISBN: 978-0134486826

12th edition

Authors: Tracie L. Miller Nobles, Brenda L. Mattison, Ella Mae Matsumura

Question Posted: