Question: Given the information in the following table, determine the processing sequence that would result using the S/O rule. Job Remaining Processing Time (days) Due Date
Given the information in the following table, determine the processing sequence that would result using the S/O rule.
Job Remaining Processing Time (days)
Due Date Remaining Number of Operations a 5 8 2 b 6 5 4 c 9 10 4 d 7 12 3 e 8 10 2