Question: relates to Project Scheduling CODE ACTIVITY IMMEDIATE PREDECESSOR (S) DURATION (DAYS) A Buy the land None B Get the construction A 40 30 permission CDEFGH

relates to Project Scheduling

CODE ACTIVITY IMMEDIATE PREDECESSOR (S) DURATION (DAYS) A Buy the land None

CODE ACTIVITY IMMEDIATE PREDECESSOR (S) DURATION (DAYS) A Buy the land None B Get the construction A 40 30 permission CDEFGH Excavate B 10 Erect building C 100 Electrical work D 10 Plumbing work D 20 Paint interior Clean up building Move in furniture D 10 E, F, G 5 H 5