Question: Using the project information listed in the table below: a) draw the AON networkfor the construction activity. b) draw the AOA for the construction activity.
Using the project information listed in the table below:
a) draw the AON networkfor the construction activity.
b) draw the AOA for the construction activity.

ACTIVITY IMMEDIATE PREDECESSOR (S) DURATION (DAYS) A B C D A E B F B 422234 G C 2 H D, E 5 I F, G 3