Question: 1. Calculate the project variable time plan using the activity data outlined below and then answer the following questions: a. What is the expected completion

1. Calculate the project variable time plan using the activity data outlined below and then answer the following questions:

a. What is the expected completion date for the project?

b. Calculate the probability that this project will complete by duration 155?

c. At what duration can we offer the management a 95% probability of being fi nished?

Task ID Predecessor a m b A … 10 15 20 B … 14 23 50 C B 40 60 30 D A 40 45 50 E D,C 30 35 42 F A 5 10 12 G B 3 16 25 H E,F,G 10 15 13 I B 7 12 13