Question: Calculate the project variable time plan using the activity data outlined below and then answer the following questions: a. What is the expected completion date
Calculate the project variable time plan using the activity data outlined below and then answer the following questions:
a. What is the expected completion date for the project?
b. Calculate the probability that this project will complete by duration 155?
c. At what duration can we offer the management a 95% probability of being finished?

Task ID Predecessor a m b A 10 15 20 B 14 23 50 B C B 40 D A 40 64 60 30 45 50 E D, C 30 30 35 42 F A 5 10 12 G B 3 16 26 H E, F, G 10 15 13 | B 7 12 13