Question: 3. As the project manager for a software development project, you are helping to develop the project schedule. You decide that writing code for a

3. As the project manager for a software development project, you are helping to develop the project schedule. You decide that writing code for a system should I"IOt start until users sign off on the analysis work. What type of dependency islt1is?

a. technical

b. mandatory

c. discretionary

d. external