Question: _______________ is a project performance measurement technique that integrates scope, time, and cost data. a. Reserve analysis b. Life cycle costing c. Project cost budgeting
_______________ is a project performance measurement technique that integrates scope, time, and cost data.
a. Reserve analysis
b. Life cycle costing
c. Project cost budgeting
d. Earned value management