Which of the following statements is false? a. A resource breakdown structure is a hierarchical structure that

Question:

Which of the following statements is false?

a. A resource breakdown structure is a hierarchical structure that identifies the project's resources by category and type.

b. Duration and effort are synonymous terms.

c. A three-point estimate includes an optimistic, most likely, and pessimistic estimate.

d. A Gantt chart is a common tool for displaying project schedule information.