Which of the following statements is false? a. A resource breakdown structure is a hierarchical structure that
Question:
Which of the following statements is false?
a. A resource breakdown structure is a hierarchical structure that identifies the project's resources by category and type.
b. Duration and effort are synonymous terms.
c. A three-point estimate includes an optimistic, most likely, and pessimistic estimate.
d. A Gantt chart is a common tool for displaying project schedule information.