Question: You cannot start editing a technical report until someone else completes the first draft. What type of dependency does this represent? a. finish-to-start b. start-to-start
You cannot start editing a technical report until someone else completes the first draft. What type of dependency does this represent?
a. finish-to-start
b. start-to-start
c. finish-to-finish
d. start-to-finish