In 2019, Tarlo Company agrees to construct a highway for Brice County over a 3-year period (2019

Question:

In 2019, Tarlo Company agrees to construct a highway for Brice County over a 3-year period (2019 through 2021). The contract price is $1,200,000, and the construction costs (both actual and estimated) total $705,000 for the 3 years. Tarlo’s estimate of progress toward satisfaction of the performance obligation at the end of each year is as follows: 2019, 20%; 2020, 75%; 2021, 100%.


Required:
1. Prepare a schedule showing the amount of gross profit that Tarlo recognizes each year assuming the performance obligation is determined to be satisfied over time.
2. Prepare a schedule showing the amount of gross profit that Tarlo recognizes each year assuming the performance obligation is satisfied at a point in time.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Intermediate Accounting Reporting and Analysis

ISBN: 978-1337788281

3rd edition

Authors: James M. Wahlen, Jefferson P. Jones, Donald Pagach

Question Posted: