Question: Complete the requirements of P 610 assuming that Westgate Constructions contract with Santa Clara County does not qualify for revenue recognition over time. Data From

Complete the requirements of P 6–10 assuming that Westgate Construction’s contract with Santa Clara County does not qualify for revenue recognition over time.



Data From Problem P6-10

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 

2021 2022 2023 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $2,400,000 $3,600,000 $2,200,000 5,600,000 2,000,000 -0- 2,000,000 4,000,000 4,000,000 1,800,000 3,600,000 4,600,000

Westgate recognizes revenue over time according to percentage of completion. 


Required: 

1. Calculate the amount of revenue and gross profit to be recognized in each of the three years. 

2. Prepare all necessary journal entries for each of the years (credit “Cash, Materials, etc.” for construction costs incurred). 

3. Prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. Indicate whether any of the amounts shown are contract assets or contract liabilities. 

4. Calculate the amount of revenue and gross profit to be recognized in each of the three years assuming the following costs incurred and costs to complete information: 

2021 2022 2023 Cost incurred during the year Estimated costs to complete

5. Calculate the amount of revenue and gross profit to be recognized in each of the three years assuming the following costs incurred and costs to complete information: 

as of year-end Billings during the year Cash collections during the year

2021 2022 2023 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $2,400,000 $3,600,000 $2,200,000 5,600,000 2,000,000 -0- 2,000,000 4,000,000 4,000,000 1,800,000 3,600,000 4,600,000

Step by Step Solution

3.52 Rating (165 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

answers Total Construction revenue 10000000 Less estimated cost 10300000 Estimated loss in the secon... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Intermediate Accounting Questions!