Question: In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

Westgate recognizes revenue over time according to percentage of completion.
Required:
1. Calculate the amount of revenue and gross profit to be recognized in each of the three years.
2. Prepare all necessary journal entries for each of the years (credit “Cash, Materials, etc.” for construction costs incurred).
3. Prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. Indicate whether any of the amounts shown are contract assets or contract liabilities.
4. Calculate the amount of revenue and gross profit to be recognized in each of the three years assuming the following costs incurred and costs to complete information:

5. Calculate the amount of revenue and gross profit to be recognized in each of the three years assuming the following costs incurred and costs to complete information:

2021 2022 2023 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $2,400,000 $3,600,000 $2,200,000 5,600,000 2,000,000 -0- 2,000,000 4,000,000 4,000,000 1,800,000 3,600,000 4,600,000
Step by Step Solution
3.49 Rating (162 Votes )
There are 3 Steps involved in it
1 Compute the amount of revenue as follows Revenue Cost incurred Contract price Total cost 2021 Revenue 2400000 10000000 2400000 5600000 3000000 2022 ... View full answer