Which of the following is unlikely to be useful in determining the stage of completion of a

Question:

Which of the following is unlikely to be useful in determining the stage of completion of a construction contract?

A. Surveys of work performed.

B. Progress payments received from customers.

C. The proportion that contract costs incurred for work performed to date bear to the estimated total contract costs.

D. Completion of a physical proportion of the contract work.