Question: Complete the following problem. The lead time is one week and the demand time fence is the end of week 3. There are 20 on
Complete the following problem. The lead time is one week and the demand time fence is the end of week 3. There are 20 on hand. The lot size is 60.

Period Forecast Customer Orders Projected Available Balance MPS ATP 20 20 19 2 21 18 3 22 20 4 20 18 5 28 30 6 25 22
Step by Step Solution
3.44 Rating (154 Votes )
There are 3 Steps involved in it
Period Forecast Customer ... View full answer