Question: Given the following product tree, explode, offset, and determine the gross and net requirements. The quantities required are shown in parentheses. The master production schedule

Given the following product tree, explode, offset, and determine the gross and net requirements. The quantities required are shown in parentheses. The master production schedule calls for the completion of 100 As in week 5. There is a scheduled receipt of 100 Bs in week 1. There are 200 Fs available. All order quantities are lot-for-lot.

D(1) B(2) E(1) A D(2) C(1) F(1) Part A Lead Time: 1

week Part B Lead Time: 1 week Part C Lead Time: 1

D(1) B(2) E(1) A D(2) C(1) F(1) Part A Lead Time: 1 week Part B Lead Time: 1 week Part C Lead Time: 1 week Part D Lead Time: 1 week Part E Lead Time: 1 week Part F Lead Time: 1 week Week Gross Requirements Scheduled Receipts Projected Available Net Requirements Planned Order Receipt Planned Order Release Gross Requirements Scheduled Receipts Projected Available Net Requirements Planned Order Receipt Planned Order Release Gross Requirements Scheduled Receipts Projected Available Net Requirements Planned Order Receipt Planned Order Release Gross Requirements Scheduled Receipts Projected Available Net Requirements Planned Order Receipt Planned Order Release Gross Requirements Scheduled Receipts Projected Available Net Requirements Planned Order Receipt Planned Order Release Gross Requirements Scheduled Receipts Projected Available Net Requirements Planned Order Receipt Planned Order Release 1 2 3 4 5

Step by Step Solution

3.39 Rating (171 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Part A Lead time 1 week Part B Lead time 1 week Part C Lead time 1 week Part D Lead time 1 week Par... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Introduction Materials Management Questions!