MPS parent X has planned order releases of 30 in weeks 2 and 4. Given the following product tree, complete the MRP records for parts Y and Z. Quantities required are shown in brackets. Z(2) Y(1) X T S Part Y Lead Time: 2 weeks Lot Size: 50 Gross Requirements Scheduled Receipts Projected Available 30 Net Requirements Planned Order Receipt
Chapter 4, Problems #9
MPS parent X has planned order releases of 30 in weeks 2 and 4. Given the following product tree, complete the MRP records for parts Y and Z. Quantities required are shown in brackets.
This problem has been solved!