Jobs A, B, and C are in queue at work center 10 before being completed on work

Question:

Jobs A, B, and C are in queue at work center 10 before being completed on work center 20. The following information pertains to the jobs and the work centers. For this problem, there is no move time. Today is day 1. If the jobs are scheduled by the earliest due date, can they be completed on time?