Question: jobs A , B , and C are in queue at work center 1 0 before being completed on work center 2 0 . The
jobs A B and C are in queue at work center before being completed on work center The following information pertains to the jobs and the work centers: Job Process time day at WC process time day at WC Due Date: A; B; and C For this problem, there is no move time between two centers. Today is day If the jobs are scheduled by shortest process time SPT rule today, how many idle days from day to the day end the date that last job is completed in work center will have?
Group of answer choices
none of them
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
