The following bill of materials represents the major components for a computer system. Complete the MRP records below. Note the following: Production plans (the MPS) for the 800 Deluxe computer system are as follows: Start assembling 2500 in week 2 Start assembling 3000 in weeks 3, 4, and 5 Start assembling 2000 in week 6 The gross requirements
Chapter 4, Problems #19
The following bill of materials represents the major components for a computer system.
Complete the MRP records below. Note the following:
■ Production plans (the MPS) for the 800 Deluxe computer system are as follows:
Start assembling 2500 in week 2
Start assembling 3000 in weeks 3, 4, and 5
Start assembling 2000 in week 6
■ The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements.
■ All scheduled receipts, lead times, and beginning inventory levels are shown.
This problem has been solved!
Do you need an answer to a question different from the above? Ask your question!
Related Book For
Introduction To Materials Management
8th edition
Authors: Arnold J. R. Tony, Gatewood Ann K., M. Clive Lloyd N. Chapman Stephen
ISBN: 978-9386873248