Question: Darshan Engineering, LLC anticipates the need for a high-speed profilometer with digital recording capability for a multi-year quality control subcontract they believe they will win

Darshan Engineering, LLC anticipates the need for a high-speed profilometer with digital recording capability for a multi-year quality control subcontract they believe they will win within the next 6 months.

Although the system costs \($43,000\) there is enough time to order a system and have it installed; management is pondering whether to lease the machine for \($9,000\) per year (in the event they lose the contract after 3 years) or whether to buy it outright.

The company MARR is 12%. Problem data are gathered below.

Project Parameter Buy Lease First cost, P $43,000 $9,000 Operating costs, OE


Project Parameter Buy Lease First cost, P $43,000 $9,000 Operating costs, OE $9,500 $9,500 Service period, n 8 years NA Salvage value, SV $7,000 NA

Step by Step Solution

3.33 Rating (159 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

SOLUTION Okay lets analyze this using NPV Buy option Initial cost ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Introduction Mechanical Engineering Questions!