Question: Consider Problem 18.12 (see Chapter 18 at www.mhhe.com/Hillier7e), which involves estimating both the duration of a project and the probability that it will be completed

Consider Problem 18.12 (see Chapter 18 at www.mhhe.com/Hillier7e), which involves estimating both the duration of a project and the probability that it will be completed by the deadline. Assume now that the duration of each activity has a triangular distribution that is based on the three estimates shown in Problem 18.12.

Use Analytic Solver to perform 1,000 trials of a computer simulation of the project on a spreadsheet.