Question: Consider Problem 16.12 (see Chapter 16 on the CDROM), which involves estimating both the duration of a project and the probability that it will be
a. What is the mean project completion time?
b. What is the probability that the project can be completed within 22 months?
c. Generate a sensitivity chart. Based on this chart, which two activities have the largest impact on the project completion time?
Step by Step Solution
3.40 Rating (163 Votes )
There are 3 Steps involved in it
a The mean project completion time is approximately 33 months b The probability of finishing in 22 ... View full answer