Question: A project is getting delayed so the project manager decides to use the float and is comparing the floats on different paths to see what
A project is getting delayed so the project manager decides to use the float and is comparing the floats on different paths to see what options he has to get the project completed as planned. Which of the following he can use to understand the situation better?
A. Free Float B. Total Float C. Negative Float D. Critical path float