Question: An Agile team is missing release dates for the last many sprints. The Agile PM is concerned and should do the followingA. Put more work
An Agile team is missing release dates for the last many sprints. The Agile PM is concerned and should do the followingA. Put more work on the plate and add on Kanban Board- ‘To Do list’
B. Move some items on the Kanban Board from ‘Being Done to
‘Done Status.
C. Ensure team improves its productivity to get more work done to meet deadlines D. Check historical velocity and change future sprints to match that velocity