Question: The third sprint is going to start for the current release due next month. The customer has requested to the PM that the team must
The third sprint is going to start for the current release due next month.
The customer has requested to the PM that the team must make some non functional changes on the technical side before working on the next piece.
What should the PM do?
A. Look for a Change Request via CCB.
B. Request Stakeholder to communicate their evaluation for the same C. Ask the team to work on the change as a self organizing empowered team D. Conduct Impact analysis for the changes on baselines.