Question: An important influential stakeholder wants the PM to quickly start the project without too much documentation but the sponsor insists that proper guidelines be followed

An important influential stakeholder wants the PM to quickly start the project without too much documentation but the sponsor insists that proper guidelines be followed that are generally recognized best practices followed over several years in companies. What should the project manager do?

A. Dig previous similar projects done and use that as a base.

B. Follow Project Management Standard- its Vocabulary, ethics, and conduct rules C. Engage with this stakeholder and “Go Agile” as it says “ No documentation”

D. Use Best Practices followed in the organization

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Management Accounting Questions!