Question: An important stakeholder has asked the Project Manager to share the details of how the remaining time will be spent on the project and come

An important stakeholder has asked the Project Manager to share the details of how the remaining time will be spent on the project and come prepared with his relevant documents or charts. What should the PM take with him before he goes to the meeting?

A. Sprint Review Meeting minutes B. Story Point Calculations C. Planning Poker Assessment D. Release Burndown Chart