Question: Building construction project work is going on. A model house was made by the builder and customers paid based on that model home only and
Building construction project work is going on. A model house was made by the builder and customers paid based on that model home only and expect to get nothing less than that and are not willing to pay more for any extra work. How should the project manager solve this?
A. Plan driven approach but non predictive will help a lot.
B. Agile is good in this scenario because each home will still be unique.
C. Hybrid will help as there are components of both fixed and movable parts to this project.
D. A waterfall and sequential approach will help.
Q105. The PM should avoid getting into undesirable patterns of behavior. All of them help build trust except one, which one is that?
A. Facilitate to resolve conflicts during meetings continuously B. During meeting build relationships and know-learn team members’ strengths C. Constant,regular, and frequent follow up several times daily with team D. Empowering team members feel empowered to make own decisions Q106. in order to solve the problem on her project the project manager has to understand two main things- the frequency of delivery and delivery of change. First one looks alright but the second looks crazy quick on the project. Which framework should she apply?
A. Frequency of delivery -high; degree of change- low- incremental B. Frequency of delivery -high; degree of change- high- agile C. Frequency of delivery -low; degree of change- high- iterative D. Frequency of delivery -low; degree of change- low- predictive