Question: Digital Processors Ltd. monitors its cycle time closely in order to prevent schedule delays and excessive costs. The standard cycle time for the manufacture of
Digital Processors Ltd. monitors its cycle time closely in order to prevent schedule delays and excessive costs. The standard cycle time for the manufacture of printed circuit boards for one of its computers is 26.4 hours. Consider the following cycle time data from the past six weeks of circuit board production.

Analyze circuit board cycle time performance in light of the 26.4-hour objective.
Week Units Completed Total Cycle Time 14,108 hours 564 14,592 hours 2 544 15,152 hours 3 553 16,598 hours 571 17,104 hours 547 552 16,673 hours
Step by Step Solution
3.40 Rating (169 Votes )
There are 3 Steps involved in it
The cycle time objective was met only in the first weekAfter th... View full answer