Question: During project execution several new things unexpectedly have come up and are going to impact the budget and schedule. How should the PM solve this
During project execution several new things unexpectedly have come up and are going to impact the budget and schedule. How should the PM solve this problem?
A. Utilize Contingency funds B. Use management reserve C. Conduct reserve analysis D. Check Funding Requirements