Question: The PM is trying to keep costs under control EV= 280K, PV= 240K, AC= 230 K, is the project under or over budget and ahead
The PM is trying to keep costs under control EV= 280K, PV= 240K, AC= 230 K, is the project under or over budget and ahead or behind schedule?
A. The project is behind schedule and over budget B. The project is ahead of schedule and under budget C. The project is behind schedule and under budget D. The project is ahead of schedule and over budget