Question: For the current project, all the activities are identified by the team but the problem is that now the PM needs to put all of
For the current project, all the activities are identified by the team but the problem is that now the PM needs to put all of it together to understand how they relate to each other and what can be done to get things done faster.
What should be PM’s least concern?
A. Create WBS B. Dependency determination C. PDM D. Leads and Lags