Question: SOURCE: ADAPTED FROM CIMA P2 PT has discovered that when it employs a new test engineer, there is a learning curve with a 75% learning


SOURCE: ADAPTED FROM CIMA P2 PT has discovered that when it employs a new test engineer, there is a learning curve with a 75% learning rate that exists for the rst 12 customer assignments. A new test engineer completed her rst customer assignment in 6 hours. A cumulative average–time learning curve model applies. How long should she take for her seventh assignment, to the nearest 0,01 hours?

Note: The index for a 75% learning curve is –0,415.