Question: The PM has a problem, there is no budget left, as delays cost extra money on the project. The PM now wants to reduce the
The PM has a problem, there is no budget left, as delays cost extra money on the project. The PM now wants to reduce the project duration without spending any extra budget, which technique he can apply?
A. Schedule Compression B. Fast tracking and Crashing C. Fast tracking D. Crashing