Question: The project schedule is being created by the project manager. In order to meet the deadline given by the sponsor he has to expedite the
The project schedule is being created by the project manager. In order to meet the deadline given by the sponsor he has to expedite the project. He is thinking about using resource optimization technique to improve productivity by reducing bottlenecks, which technique PM can apply?
A. Resource mobilization technique B. Resource leveling C. Resource smoothing D. Crashing or fast tracking