Question: The PM is working on a project and just finalizing planning. The sponsor has requested a meeting and wants to look at Performance Measurement Baseline.
The PM is working on a project and just finalizing planning. The sponsor has requested a meeting and wants to look at ‘Performance Measurement Baseline’. What should the PM carry with him to the meeting so that he can present and answer any questions that sponsor and stakeholders might have?
A. Scope Baseline & Schedule Baseline B. Scope Baseline, Risk Baseline C. Scope Baseline, Schedule Baseline, & Cost Baseline D. Scope Baseline, Quality Baseline, Schedule Baseline, Cost Baseline