Question: The project is having a problem as items are defined at a high level only making it difficult to estimate duration and cost for each
The project is having a problem as items are defined at a high level only making it difficult to estimate duration and cost for each activity. The team will be helping the project manager break down larger pieces of requirements into smaller and manageable chunks. How should the PM solve the problem?
A. Decomposition B. Expert judgment C. Breakdown structure D. WBS creation