Question: A contingency reserve is set-up for what types of risks? a. risks that have been passively accepted b. risks that have been actively accepted c.
A contingency reserve is set-up for what types of risks?
a. risks that have been passively accepted
b. risks that have been actively accepted
c. as part of a mitigation strategy
d. as part of an avoidance strategy